Building The Foundation –BOHORICA
Foundation for Support
The Bohorica Project in Costa Rica is moving forward in its construction, and the next step is building the foundation walls. The team at Cavu Land Corp working on the project is using concrete blocks to construct the foundation walls, which will provide a strong and durable foundation for the rest of the house.
To start the process, the construction team marked out the outline of the foundation walls and dug a trench around the perimeter. The trench is then filled with rock and reinforced steel to create a solid base for the walls. The team then began laying the first row of concrete blocks to provide strength and stability.
As the walls are built upward, reinforcing steel and concrete is added to provide additional support. The steel bars are embedded in the concrete blocks and extend into the surrounding soil, creating a solid foundation that can withstand the weight of the building above.
The process of building a concrete foundation involves several steps:
Reinforcing involves adding steel bars or other reinforcement materials to strengthen the foundation.
Pouring is the process of adding concrete to the formwork to create the foundation itself.
As the project progresses, Cavu Land Corp is overseeing the construction process to ensure that everything is on track and the work is being done to the highest standards. With their expertise and attention to detail, the team at Cavu Land Corp is helping to bring the vision for Casa Bohorica to life.